The Building Of The New
Syracuse Suds Factory
Continued....
The next stage of
construction was to build the Syracuse Suds Factory. We started framing the
basement and the first floor.
Here the framing has started
on the 1st floor.
After the framing was
complete dry wall was delivered and was there a lot of drywall.
During the time we were
framing the 1st Floor Nimo was installing a new Electrical service and gas line
during the install.
They happened to hit one of
their own gas lines and had to evacuate the
surrounding buildings and close off the street while the fire dept. came in so
Nimo could shut down the leak.
As was stated before the
only way up or down in the building was by ladder and a hoist system here is Billy checking out the brick work.
Here I am doing the same.
Once the framing was
complete it was time for the floors. Here is the start of the
brewroom floor.
As the floors were going
down the outside of the building was getting a face lift as well.
After the tile floors were
in place it was time to move.... We moved everything from the bar to the light
fixtures.
After everything was moved
it was time to start painting.
When the painting was
finished we started installing all the equipment.
As all the items were being
installed it was time to open the arched windows.
the final step to the suds
factory was the floor.
As the old era ends. A new era
begins.
[next stop on the tour...]
|